The Bissell Bridge Has Both Lanes Back. The Contract Runs Another Year.

As of Oct. 8, 2026, westbound I-291 between Exit 2 in South Windsor and Exit 1D in Windsor has two full travel lanes again. That ended almost four months of single-lane traffic over the Connecticut River. By the end of October that's three weeks of two-lane traffic, and the morning trip toward I-91 probably feels back to normal. It is not finished. The Connecticut Department of Transportation says the current setup will hold "until Spring 2027," and the rehabilitation contract doesn't end until Friday, Nov. 12, 2027, according to CTDOT's fall update.

So the project is less than a third done by the calendar. Work started June 18, 2026. Counting to the November 2027 finish, that's about 17 months of contract time, and only a little over four of them are behind us. For anyone who uses the bridge, the useful thing to know is where the backups formed this summer, which was the South Windsor side. That spot is the one to watch when work picks up again.

How the summer played out

CTDOT carried out the westbound work in three stages:

  • June 18: A June 9 advisory cut westbound traffic between Exits 2 and 1D from two lanes to one 11-foot lane "through the summer season," with the left lane closed.
  • Sept. 9: The closure moved from the left lane to the right lane. Traffic still had one 11-foot lane, Patch reported the day before the change.
  • Oct. 8: Both lanes reopened as two 12-foot lanes, with a four-foot right shoulder and a five-foot left shoulder. CTDOT says this setup stays in place until spring 2027.

All three notices covered westbound traffic only. None of them announced eastbound lane closures, planned overnight work, or ramp closures for the project. That fits how the summer went for South Windsor. The pinch fell on the trip out of town in the westbound direction, toward Windsor, I-91 and Bradley. The trip home was largely left alone.

The contract went to McNamee Construction Corp. for $16,874,000 on May 5, 2026, under CTDOT Project No. 0164-0245. CTDOT's project page still shows an older pre-award estimate of about $29.75 million. That number has been replaced by the award figure.

The backup formed at Exit 2

This summer's bottleneck was on the bridge, but the trouble showed up on the South Windsor approach, before the river. On Aug. 31, a nine-vehicle crash near Exit 2 shut the westbound lanes for more than five hours, the Journal Inquirer reported. WFSB reported that police also closed the westbound I-291 on-ramps from Route 5 while crews worked the scene. Those ramp closures were part of the crash response, not a planned detour.

In that same Journal Inquirer story, Brian Peck, assistant chief of the South Windsor Volunteer Fire Department, explained the stretch of road this way:

"The lane closure has been causing traffic to back up as far as Exit 2. While there are electronic messaging signs warning to slow down prior to Exit 2, there continue to be accidents in this area when drivers cresting the hill at Exit 2 are suddenly coming upon stopped or slow-moving traffic with little time to react. This combination of limited sight distance and recurring traffic congestion has contributed to multiple serious crashes in this area."

If you get on I-291 from Route 5, this is your stretch of road. With one lane open, the line of cars reached back over the hill at Exit 2, where drivers couldn't see it until they were close. The lane shift on Sept. 9 kept one lane closed, and WFSB's coverage of that change told drivers to slow down through the area. If westbound lanes close again in 2027, expect the same hill to be the trouble spot, since the road itself won't have changed.

Why it's done in stages

The lane closures make more sense once you know what the project is for. The Bissell Bridge was built in 1958 and rebuilt in 1993. It carries four lanes, runs 1,682 feet end to end, and has a longest single span of 120 feet. CTDOT's project page says the superstructure had an overall condition rating of seven, which means Good, at its last evaluation in 2021. The goal is to bring the bridge to a "State of Good Repair." The work list covers steel and deck repairs, new deck joints, substructure repairs, a waterproofing membrane under a new asphalt overlay, spot painting, and replacement of missing anchor bolts on the bearings.

Closing a lane at a time was not a given. At a virtual public meeting in February 2024, CTDOT said a full detour was possible "if the traffic volumes are too high to accommodate staged construction," and that the decision would come during final design, per the meeting minutes. The Hartford Courant reported at the time that traffic studies in 2025 would show whether the work could be phased so that no more than one or two lanes closed at once. The summer that followed was the phased version. Drivers on Route 5 lost one lane at a time instead of being sent onto a detour.

The same minutes cover the bridge's light poles. Someone at the meeting asked why working lights were being replaced. CTDOT said plows kept hitting the poles in winter because they stand so close to the roadway, and the plan was to set the new ones farther back.

What happens in spring 2027

CTDOT has given an end date for the current setup and nothing more. The Oct. 8 notice says two westbound lanes will stay "until Spring 2027" and warns that "modifications or extensions to this schedule may become necessary due to weather delays or other unforeseen conditions." In its Oct. 9 story on the reopening, Patch said the rehabilitation work is still going on. Patch made a related point back in August. The November 2027 end date doesn't mean the bridge stays at one lane until then, because CTDOT tied the single-lane setup to the summer 2026 phase.

CTDOT hasn't yet answered these questions about 2027:

  1. Will lanes close again when the work starts back up, and in which direction?
  2. Will eastbound traffic toward South Windsor be affected at any point?
  3. Will the bridge's walkway stay open during construction? CTDOT's project page lists an eight-foot "left curb or sidewalk" width.

CTDOT's project page sends questions to Customer Care at [email protected] and asks that emails include the project number, 0164-0245. The next phase will be announced on the CTDOT construction advisories page, the same place the June, September and October notices appeared.

At The Knurek Team, we keep track of projects like the Bissell Bridge because how long the trip to Windsor or Bradley takes is part of what a South Windsor home is worth to the people who live in it. If you're thinking about selling or buying, and you want someone who knows how projects like this one affect your part of town, start with a free home valuation and we'll go through it with you.